COMPANY:
WORK:
CLIENT:
DATE:
FINALIZED

     

LAYING OF TRACK OF THE SESTAO-PORTUGALETE SECTION LINE 2 BILBAO METROPOLITAN RAILWAY CLIENT CONSORCIO DE TRANSPORTES DE BIZKAIA BUDGET 2.615.858 € FACULTATIVE DIRECTION Iñaki Erkoreka (CTB) PERIOD OF EXECUTION January 2006 - June 2006 ESTADO Finalizada LOCATION Sestao-Portugalete,Vizcaya
DESCRIPTION

The Sestao-Portugalete section consists of approximately 1.64 km. of metric-gauge double track.

We laid 2,174 m. of track on a concreted plate with  UIC 54 rails and bi-block sleepers with elastic seating, according to the Stedef design, for embedding in concrete. We installed one B1-type double diagonal.

The works also included executing the drainage network and installing the dry standpipe.

 

metro
Foto 2
Foto1