Bilbao Tram Basurto-Atxuri line
Client:
Budget:
Project management:
Execution period:
Status:
Location:
Basque Government, Dept of Public Works
12,687,365 €
Interbiak
July 2005 - February 2007
Completed
Bilbao, Vizcaya

Description

Laying of 3,840 metres of urban line with RI60N rails with Sedra coating, finished with cobblestones or asphalt. Laying of 3,124 metres of green line with UIC54 rail on Edilon blocks and with earth infill. Construction of 4 switches and a double diagonal with the urban track system.